| 16R Glidepath | | Construction of Runway 16R Glide path equipment building. | |
| A380 Apron Works Bay 61, 63 | | Excavation, Demolition Sheet piling and Slurry Backfilling of Fuel Lines. | |
| A380 Project | View Gallery | This project was undertaken with the introduction of the Airbus A380 to Sydney Airport. When compared to existing passenger aircraft, the A380 is larger in height, length, wingspan, weight & passenger capacity.
To accommodate the A380 aircraft, Sydney Airport Corporation Limited (SACL) and JUHI, an incorporated joint venture between BP, Caltex, Mobil, Qantas & Shell, require the modification of Aviation Hydrant Systems at up to 10 Parking Bays to commence 2006 to 2008 | | Location: Sydney Airport | | Duration: 24 Months | | Cost: $4,000,000.00 |
|
| Aircraft Waste Dump-Civil Works | | Bulk excavation, sheetpile shoring installation & removal, dewatering and asphalt. | |
| Bay 24 A380 Apron Pavement Works | | Remove and reinstatement of flexural concrete aircraft apron. | |
| Bay 55 A380 Apron Pavement Works | | Remove and reinstatement of flexural concrete aircraft apron. | |
| Bay 73 Apron Pavement Works | | Construction of new flexural concrete aircraft apron. | |
| Berala/Carramar Tennis & Rectin Club | | Excavation, Kerb & Gutter Works, Stormwater Drainage, Construction of asphalt pavement. | |
| Campbell Hill Pioneer Reserve | | Construct new access road, concrete weir, Sediment basin & Trash rack. | |
| Charles St & Parkes St Parramatta | | Construct a new 4 lane carriageway, Concrete Retaining walls, stormwater drainage, earthworks. | |
| Charles Street | View Gallery | Citywide Civil Engineering was engaged by Parramatta City Council for this important part of road infrastructure due to the complicated conditions that exist as a result of the location of the site.
The project involved clearing & demolitions, bulk excavation, concrete retaining walls & architectural noise walls, pedestrian fencing, screw pile & beam construction for new footway, kerb & gutter, stormwater drainage, slip lane construction, new road pavements, traffic loops, line marking & major traffic control & management. | | Location: Parramatta | | Duration: 6 Months | | Cost: $1,500,000.00 |
|
| Contractors Compound Services | | Reticulation of Sewer, Water, Electrical and Comm.\'s to contractors compound. | |
| Domestic Multi Story Carpark | | Construction of new vehicle entry/exit driveways, Relocation of Car wash area. | |
| Gate 25–Sec Access Syd Intel Term | | Flexible pavement, Chainwire fencing, Supply & Install new automatic swing gate. | |
| Gate 31 & 32 – Aerobridge Upgrade | | Demolish existing pavement, construct new Aerobridge footings and raised Bondek concrete slab. | |
| GBAS | | Construct of Piled Footings, Slabs & Shed Installation. | |
| Helipad | | Construction of Helipad and perimeter road. | |
| Hydrant Modifications S.I.T Bay 22 | | Removal and replacement of concrete aircraft apron. | |
| Island 39 Regrading Works | | Removal of CLER and Fire station Foundations. | |
| James Ruse Drive | | Extension of right hand turning lane. | |
| JUHI Bay 10, 5, 9, 4, Shell Works | | Excavation, Demolition Sheet piling and Slurry Backfilling of Fuel Lines. | |
| JUHI Bay 24 Shell Works | | Excavation, Demolition, Sheet piling and Slurry Backfilling of Fuel Lines. | |
| JUHI Bay 55 Shell Works | | Excavation, Demolition and Slurry Backfilling of Fuel Lines. | |
| JUHI Bay 55 Shell Works | | Excavation, Demolition and Slurry Backfilling of Fuel Lines. | |
| JUHI Road Pavement Repairs | | Demolition & Repair of Pavement. | |
| Liverpool Golf Club Hollywood Drive | | Stormwater Drainage, K & Gr, Earthworks, Subbase. Asphalt pavement. | |
| Mitchel Road Drainage | | Stormwater Drainage including installation of Atlantis Cells and minor roadworks. | |
| Moss Vale Road, Bomaderry | | Construction of additional turning lane. | |
| NLA Runway Cabling (Pit & Duct) | | Trenching, Reticulation of Electrical Pits & Ducts for NLA taxiways. | |
| NLA Shoulder Pavements Trial | | Demolition of Pavements, Protection of Ex. Services, Construction to Airside Road. | |
| Perimeter Lighting | | Trenching, Reticulation of Electrical Cabling, Lighting, Pits & Ducts. | |
| Pier B Cutback Plinth | | Extension of existing concrete plinth. | |
| Qantas A380 Hard Stand | | Construction of Piles and hardstand for A380 Northern pond. | |
| Qantas Tug refuelling | | Demo of fuel and tanks and removal of contaminated material. | |
| Racetrack Conveyors at Terminal T2 | | Concrete plinth demolition and replacement. Asphalt reinstatement. | |
| Realignment of Ross Smith Avenue | | Demolition, Pavement Works, Reticulation of Stormwater, Electrical and Comm.\'s. | |
| Rocky Point Road | View Gallery | This project was undertaken due to local flooding problems in the main shopping district of Ramsgate. Due to numerous complaints from shop operators & local residents Kogarah Council undertook the work to alleviate the problem.
The Contract was awarded to Citywide Civil Engineering due to the location of the works being on one of Southern Sydney's main arterial roads. As a result the work had to be carried out in limited working hours in which the worksite had to be opened to traffic at the completion of each shift using steel plates. | | Location: Rocky Point Road Ramsgate | | Duration: 2 Months | | Cost: $150,000.00 |
|
| Ross Smith | View Gallery | Works comprise of a re-aligned section of Ross Smith Avenue and associated road works on Arthur Butler Road due to this section of road being a major "black spot" for the likelihood of accidents.
The various elements of the works included demolition, pavement works, line marking, reticulation of stormwater, electrical and communications services, road signage, street lighting, grass restoration, turfing and the construction of a flood protection earth bund wall. | | Location: Ross Smith Avenue | | Duration: 3 Months | | Cost: $600,000.00 |
|
| Runway 25 - RESA | | Construction of the pavements of the Airport runway surface and RESA surface. | |
| Runway Ends Compliance Works (RESA) | | Excavation, construction of pavement, turfing and asphalt. | |
| Sutherland Shire Council | | Road construction and associated works. | |
| SW Sector Early Works | | Demolition of Struct, Pavement Works to Airside Road & Fire Access, Fencing & Hydromulching. | |
| Sydney International - ALPHA 5 | | New Generation Aircraft Fillets. | |
| T1 High Mast Flood lighting | | Erection of Floodlight, Construct of Footings, Electrical Pit & Duct Works. | |
| T1 Pier C | | Demolition of existing plinths and carousels and construct new laterals. | |
| T1 Pier C (Stage 5) | | Demolition of existing plinths and carousels and construct new laterals. | |
| T1 T2 Floodlighting | View Gallery | This project was undertaken due to the existing floodlights and associated electrical works at Sydney Airport were designed & installed at various times over the last 20 years for the type of aircraft operating at the time.
The general illumination on some Terminal parking bays was below that required by the Civil Aviation Safety Authority\'s Manual of Standards (MOS) for the type of large bodied aircraft now using the bays. | | Location: Sydney Airport | | Cost: $2,500,000.00 |
|
| T2 Domestic Terminal Trans Mod | | Demolition of Pavements, Kerb and Gutter, Stainless Steel Corral Construction. | |
| T2 Retail Redevelopment | | Construct Concrete Footings and reconstruction rigid & flexible pavements. | |
| T2 Term Gates 32-34 Retail Development | | Construct of rigid & flexible aircraft pavements, Stormwater struct, light pole & aerobridge footings. | |
| T2 Terminal Pier A&B -Syd Dom Term | | Erection of Floodlight, Construct of Footings, Electrical Pit & Duct Works. | |
| T2 Toilet Block External Works | | Excavation, Footings, Steelwork, Suspended Slab, Cladding Construction. | |
| Taxiway Bravo & Charlie | | Rehabilitation of both Taxiways Bravo and Charlie and Drainage Works. | |
| Test Rolling of Runway Flanks | | Test rolling of runway flanks. | |
| Tilt Tray Baggage Sorter Platforms | | Steel Fabrication & Installation of Steel Platforms to Baggage Sorter T1. | |
| Toilet Block | View Gallery | | Citywide Civil undertook a project for Sydney Airports Corporation at Sydney Airport International terminal between November and December 2006 where we were involved in excavation, demolition and slurry backfilling of fuel lines of Bay 57. | | Location: T2 Pier A Toilet Block Structure & External Works | | Duration: 3 months | | Cost: $300,000.00 |
|
| Upgrade of 11kV Cable | | Excavation and installation of a high voltage cable. | |
| Warcoo Ave, Gymea | | Widening and sealing of existing local road. | |
| Windsor Flood Evacuation | | Earthworks, Drainage Works, Roadworks and level Crossing construction. | |
| Domestic Precinct Public and Economy Hire Car Pick-up Relocation | | The existing Economy Hire Car Pick Up is to be relocated between Fourth and Fifth Streets with own dedicated access controlled entry/exit point. The primary purpose is to provide a minimum 19 undercover pickup spaces. The existing T2 Arrivals Pick-up Area is to be relocated between Fourth and Fifth Streets with access controlled entry/exit point and free entry for a limited time. The primary purpose is to increase the Public Pick up capacity and reduce traffic congestion within the Domestic Precinct by constructing a minimum of 53 car spaces including 16 undercover car parking spaces, two undercover public waiting areas and covered walkway. The existing T2 Arrivals Pick-up Area is to be changed to premium limousine area with an access controlled entry point. | |
| Runway 25 - RESA Deck Slabs, Fender Walls & Cross Beams | | Part of the RESA is to be supported on a series of land bridge structures that are required to span over the existing Southern and Western Suburbs Ocean Outfall Sewer (SWSOOS), the M5 East Tunnel, and the airport perimiter road which is to be realigned as part of these works. The land bridge structures are constructed of precast planks supported on the headstocks, and CFA and bored piles.
| |
|